WASTEWATER LEAK - PROSSER STREET, TITAHI BAY
Wellington Water crews responding to a wastewater leak on Prosser Street, Titahi Bay

Our team have responded to a wastewater leak at the corner of Prosser Street and Titahi Bay Road. 

Excavation is currently underway. The pump station is operating but will need to be shutdown before repair. Plans to divert the wastewater flow away from the pipe is being developed as the pipe will also need to be shutdown before repair.

There has been an earlier discharge into the stormwater network. This has now stopped with sucker trucks managing the flow, preventing wastewater entering the stormwater network. Signage has been placed at the outlets into the harbour and water quality sampling will be underway.

Traffic management has been set up on Titahi Bay Road. One southbound lane has been closed.

Water Networks / Connaught Terrace Water Pipe Replacement

Connaught Terrace water pipe replacement

Wellington Water, on behalf of Wellington City Council, is proactively replacing approximately 25 metres of drinking water pipe on Connaught Terrace, Brooklyn.
Overview
Background
All Updates

Wellington Water, on behalf of Wellington City Council, is proactively replacing approximately 25 metres of drinking water pipe on Connaught Terrace, Brooklyn.

100% Complete
Start Date
26/01/2026
End Date
16/02/2026
Contact:

If you have any questions about this work, please contact:

Wellington Water, 04 912 4400

Latest Updates

16/02/26 Works completed

02/02/26 Pipe replacement underway this week

Wellington Water, on behalf of Wellington City Council, is proactively replacing approximately 25 metres of drinking water pipe on Connaught Terrace, Brooklyn.  

Since the installation of this water main in 2021, we have identified possible risks with the type of welds used in its construction. This project will minimize the risk of future failure, which would create significant disruption and loss of water supply to residents. 

The works involve: 

  • excavations in the road between 12 and 16 Connaught Terrace to identify and measure the length of pipe that will be replaced 
  • re-sealing the road temporarily while the new section of pipe is assembled and tested off-site 
  • returning in February to replace the pipe, which will require a water shutdown 
  • reinstating the road surface one the replacement is complete. 

 

One lane will be closed with a stop-go system in place during working hours. The lane will be reopened in the evenings and on weekends. Residents who need to enter or leave their driveways will be guided by traffic controllers. 

The works are being undertaken by Fulton Hogan. 

All Updates

16/02/26 Works completed

The pipe replacement works on Connaught Terrace have now been completed. Our contractors, Fulton Hogen, successfully removed and tested a section of pipe that contained several welds. This was a proactive step to reduce the risk of future faults and outages. 

The results from this testing will inform our future maintenance planning and ensure we continue to manage the network responsibly.

We appreciate the patience and understanding of local residents during these works. 

02/02/26 Pipe replacement underway this week

After assembling the new pipe section off site, our contractors Fulton Hogan are returning to Connaught Terrace this week to install it.

There will be a drinking water shutdown on Wednesday 4 February so the existing pipe can be safely disconnected and removed. We expect the water supply to be interrupted for about four and a half hours.

This work is being done proactively to prevent issues arising in future due to the type of welds originally used in constructing the water main.

The trench will be backfilled and the road surface will be rEinstated on Thursday, with all works completed and the road clear and open from Friday.