WASTEWATER LEAK - PROSSER STREET, TITAHI BAY
Wellington Water crews responding to a wastewater leak on Prosser Street, Titahi Bay

Our team have responded to a wastewater leak at the corner of Prosser Street and Titahi Bay Road. 

Excavation is currently underway. The pump station is operating but will need to be shutdown before repair. Plans to divert the wastewater flow away from the pipe is being developed as the pipe will also need to be shutdown before repair.

There has been an earlier discharge into the stormwater network. This has now stopped with sucker trucks managing the flow, preventing wastewater entering the stormwater network. Signage has been placed at the outlets into the harbour and water quality sampling will be underway.

Traffic management has been set up on Titahi Bay Road. One southbound lane has been closed.

Water Networks / Pitt Street Wastewater Renewal

Pitt Street wastewater renewal

Overview
Current status

On behalf of Wellington City Council, we are renewing the wastewater pipeline in Pitt Street to reduce leaks, prevent blockages and increase the resilience of the network.

Start Date
6/06/2023
End Date
5/09/2023
Contact:

If you have any questions about this work, please contact:

Wellington Water, 04 912 4400

Work commences 6 June 2023 and will take approximately 17 weeks to complete.

Our contractors G.P.Friel Limited will be on site between the following hours: 

7am to 5pm Monday to Friday

7am to 12pm Saturday

Some traffic and parking restrictions will be in place during work hours and traffic management will be in place. Please take care and follow the guidance around the worksite for your safety and the safety of our crews.